|
<Previous
Next>

LP Gas Tank and Supply Line Installation - completed project.
By Kirt Blattenberger, RF Engineer, RFCafe.com webmaster
In mid-June (2026), I detected a rather strong odor of LP gas in the vicinity
of an 300-gallon underground storage tank in my daughter's yard. I had detected
it a few times before, usually after a strong rain. My guess is that the gas permeated
the soil during a dry spell, then was forced out as water saturated the ground.
LP gas if heavier than air, so it would tend to prefer residence in the ground if
its source was there.
The tank, of
late 1980s vintage, is buried about 30 feet from the house, which in and of itself
is OK per code, but the disturbing part is that my grandson's play yard is right
over top of it. Previous attempts to "scare" the adults into relocating the tank
had no effect. This time, though, there was no ignoring it. The fuel level indicator
was showing a rapid loss of content, and the only thing using the LP gas is a 26 kW
Generac whole-house generator that only runs every two weeks for 12-15 minutes to
do a self-check and charge the starting battery. Action was needed immediately.
It has only been a few months since the underground 240-volt AC feeder line to
the farm buildings lost one leg (down to 120 volts). That necessitated a complete
redo of the electrical supply system, which included burying a new 150-amp feeder
line in PVC conduit to the first building, and replacing a rickety overhead feed
to another group of buildings (the property is a small, retired dairy farm). Details
of the endeavor can be found at
Underground Service Cable and Circuit Breaker Panel Replacement.
Now, it was time to switch hats from electrician to gas technician. My experience
with electrical work is extensive, but with gas, not so much - especially for such
a major undertaking. Fortunately, a huge amount of research, including local codes,
industry best practices, and manufacturers' data, provided the necessary information.
End-to-end LP gas line installation trenches.
LP gas line burial depth.
LP gas line run from LP gas tank to launch into ground. "Tee"
fitting with plug installed to accommodate possible future need. Note sediment
trap. I think maybe the BigBlue leak detector fluid cause the rust to form
on the iron pipe fittings.
Secondary (low pressure) LP gas regulator.
LP gas line connection to 26 kW Generac generator. Note sediment
trap.
Entire LP gas line path from ground exit to generator.
Original LP gas line connection from underground storage tank.
The first course of action was to procure an above-ground LP gas tank. We decided
that a 330-gallon job would be sufficient to run the generator for at least a week
with low demand. LP gas tanks are outrageously expensive. If you can find a used
one - which I did not want - the cost would be around $1,000-$1,500. A spanking
new 330-gallon tank cost $2,600. Ouch. There was already a 12'x12' concrete pad
located about 50 feet from the generator and about 150' from the house, so we chose
that. The generator, as the photos show, is in a fenced-off area in one of the horse
pastures, so the tank didn't want to go there.
Planning the installation, generating a layout and parts list, and procuring all
the pipe, fittings, valves, pressure regulators, test instruments, pipe tape and
dope, and research took a little over a week. That included driving 30 miles to
get the tank into the back of a Chevy Silverado 2500 pickup truck. A tractor easily
lifted it from the truck bed and set it in place.
I hand-dug a trench in this nasty, hard red clay ground to a depth that put the
top of the 1" diameter yellow gas pipe no less than approximately 16" below grade.
Code says 12" minimum. There hadn't been much rain for months, so the ground was
like baked adobe. In most of it, I needed to break the surface down a couple of
inches, run water in it and let it soak for a while, then dig some more. That process
was repeated a few times. For about half the distance, there was thin layer of crushed
rock just below the surface from where the farmer had spread it around the concrete
pad - part of a much larger structure that once held a huge milk storage tank.
If you are not familiar with gas supply installations, two regulators are required.
A high pressure regulator at the storage tank output connection drops pressure from
60-160 psi in the tank (depending on temperature) down to 10-12 psi According
to industry-wide code, and then a low pressure regulator drops that pressure down
to 11-13 WC. WC stands for "water column," which is equivalent to 0.36-0.43 psi†,
or 2.49-2.99 kPa. The regulator on your patio gas grill has a combined 2-stage
regulator that does the same thing. Code requires that the low pressure regulator
not be located less than 5 feet from any source of ignition. That is because it
has an over-pressure relief valve that could potentially release gas into the air.
That meant at lest 5 feet from the generator, but there are also 240-volt electrical
panels in the area for the automatic switchover gear and a 200-A main circuit breaker
for the entire property, so the regulator ended up about 7 feet from the generator.
Also, the manufacturer wants the regulator at least 2 feet from the ground to prevent
dirt and grass from being splashed up into the relief outlet on the bottom of the
regulator.
Most of the installation was completed in a day. I did not start until all the
components were on hand. 1" black pipe and yellow polyethylene pipe was used from
the LP gas tank connection over to the second-stage regulator, then 3/4" black pipe
was used from there to the generator. An insulated tracer wire was laid in the
trench with the pipe. The most expensive single part other than
the high-pressure(1st stage) and low-pressure (2nd-stage) regulators (~$120 each) was the 1" plastic-to-iron-pipe
sweep bend transitioning from the underground polyethylene pipe to above-ground
iron pipe - about $75 each (2 required). Couplers for the plastic pipe are $30 each
(qty. 2). Black iron pipe cost about $5-6 per foot. Ells, couplers, and adapters
were around $5-10 apiece, and the 1" unions (qty. 2) were a whopping $30 each. I
kept the number of bends to a minimum, but in all ended up with around 6*90°
= 540° worth of bends, only 3 of which were were hard 90° bends, the other were
sweeps. Total cost of parts was around $600. Special equipment was about $200 for
digital manometer (aka pressure gauge), pipe flaring tool (for copper pipe between
LP gas tank 1st stage pressure regulator and black iron pipe fittings), and leak
detection fluid.
Yellow pipe dope was used on all the joints, and they were tightened to what
I thought, based on research, was ample torque, without being too aggressive. Turns
out, I should have been a lot more aggressive. After charging the line with air
to 15 psi, leaks appeared all over the place. Most were cured with more torqueing
of the joints. Some required disassembly, wrapping with yellow gas tape, doping,
and reassembling with plenty of torque. Finally, pressure held for many hours. Then
after sitting exposed to the hot sun all day and then cooling, tiny leaks began
appearing.
I started out using some brush-on leak detector fluid, but even though it showed
no signs of leaks anywhere in the path, the system would lose 2-4 psi overnight.
I discovered the mechanical pressure gauge (new, 15 psi max) was leaking a
smidge internally so it was isolated from the system by a small valve. Still, a small
leak persisted. Out of desperation, I paid $25 for a spray bottle of
BigBlue Microleak Detector.
It has a lower viscosity and much higher surface tension, which allows bubbles to
grow over hours without popping. With that, I was able to find the small leaks and
fixed them with a combination of yellow gas tape and yellow gas dope, and a lot
of torque. Finally, after four days of chasing down microleaks, the pressure held for
two days.
Inspection only requires the system to be charged with 150% of the normal working
pressure (1.5 x 10 psi = 15 psi) and for it to not indicate any loss after
15 minutes. This experience has me believing that there are a huge number of gas
piping systems out there that passed inspection, but have some degree of leakage.
I can't be the only schmo who has had to deal with so many microleaks.
Yesterday, about three weeks after beginning the process, was the moment of truth. After having 100 gallons delivered into the
330-gallon LP gas tank, I purged the air from the line all the way to the generator
input (out through the pressure test port on the generator itself), and fired her
up. After about 45 seconds of cranking (in two time segments), the beast took off
- running, that is, not into space as it blew up ;-)
In order to help reduce exposure to severe heating and cooling cycles, I installed
a shade over most of the exposed pipe.
Mission completed. Total project parts cost was around $3,500. Now, I'll monitor the joints with BigBlue to make sure no
leaks creep in.
One more note here on the generator installation. A 12-kW, 240-volt Guardian
generator was in place when my daughter and son-in-law bought the retired dairy
farm a few years ago. It was not really sufficient to service the house during severe
cold weather when the auxiliary resistance heat coils might be needed to supplement
the heat pump. It was very unreliable and failed to start when needed during storms
with heavy rain - just when it was needed most. We went to 26 kW based on my demand calculations and a plan
to limit energy usage whilst on generator power.
The original gas line system had a 120' length of 1/2" copper pipe buried in
the ground between
the underground storage tank and the generator (in some places less that 6" below
the surface!). The Generac manual dictates 1" pipe for runs between 40' and 160',
so that old line would never have been able to supply enough gas under full load, or even
half load. Even though around $800 worth of LP gas leaked from the old tank, I consider
the entire event a blessing in disguise from safety, reliability, and performance
perspectives. I'm sure glad that's all behind me!
† Derivation of WC in equivalent PSI: To convert inches
of water column (in WC) to psi, use the fact that a 1‑inch‑tall column of water
with a 1 sq. in.
cross‑section weighs ≈ 0.03613 lb (since water density ≈ 62.4 lb/ft³, and 1 in =
1/12 ft, so weight = 62.4 lb/ft³ × (1/12 ft) × 1 in²×(1/144 ft²/in²) = 0.03613 lb).
Pressure is that weight divided by 1 in², so:
psi = inches WC / 27.68 or psi=inches
WC * 0.03613
For 11" WC:
- Using the division: 11/27.68≈0.3974 psi
- Using
multiplication: 11×0.03613=0.3974 psi
The exact conversion factor depends
slightly on water temperature (density changes), but 27.68" WC per psi (or
0.03613 psi per in WC) is standard for near‑room‑temperature water.
Disclaimer: The author is not a licensed gas contractor, and
this account describes a personal project completed and believed to be in compliance
with local codes at the time of installation. Gas piping work involves serious risks
of fire and explosion. This article is for informational and educational purposes
only and does not constitute professional advice. Always consult a qualified, licensed
professional before undertaking any gas-related work. Follow all applicable local
codes and manufacturer instructions.
|